Is Your Building A Good Candidate for Cogeneration (CHP)?

What Cogeneration Actually Does

Combined heat and power — cogeneration, or CHP — puts a generator in your building and then does something a power station cannot: it recovers the engine's waste heat and pipes it into your space heating, domestic hot water, process loads, or absorption cooling.

A conventional arrangement wastes energy twice. A distant power plant discards most of its fuel energy as heat at the stack and cooling tower, then loses several percent more moving electricity to your building. Meanwhile your boiler burns separate fuel to make the heat you need. CHP collapses those two purchases into one fuel stream, which is why a well-matched system converts a much larger share of the fuel it burns into energy you actually use.

The catch is in the phrase *well-matched*. CHP economics depend less on the equipment than on the building. That is what the quiz is for.

What Makes a Building a Good Candidate?

Four conditions carry most of the outcome. The quiz asks you directly about three of them; the fourth — how much of the recovered heat your building can actually use — is inferred from the building type you select, using typical utilization for that category.

A steady year-round use for the recovered heat.

This is the single biggest factor, and the one that most often decides a project. Recovered heat is where a large share of the savings come from, and a building that can use it all year — not just in winter — captures that value every hour the unit runs.

Rather than ask you to estimate this, the quiz infers it from your building type. A hospital is assumed to use about 85% of the available recovered heat, a hotel 75%, a multifamily building 70%, an office 40%, a retail unit 35%. Those figures reflect what buildings of each type typically do with continuous hot water, process load and heating. The result screen shows the figure it used, so nothing is hidden.

The consequence is that thermal suitability sets a ceiling. An office or retail building will not be presented as a strong candidate on the strength of long hours and a large electricity bill alone, because without somewhere for the heat to go the economics change fundamentally. If your building is unusual for its category — an office with a pool, a data hall with absorption cooling, a retail site with significant process load — say so when you contact us, because the screening will have understated you.

Long operating hours.

A CHP unit earns its keep by running. Facilities operating around the clock, or on extended shifts, accumulate the run hours that pay back the installation. Standard business hours alone rarely produce enough. As a rough threshold, prospects above roughly 5,000 equivalent full-load hours per year tend to screen well.

A meaningful and reasonably constant electrical load.

The system is sized against your building's demand, not against your peak. If your average load is small, even the smallest unit in our range would be oversized for the site.

A usable fuel supply.

Our units run on natural gas, propane, or biogas. Sites with no fuel service, or with fuel availability not yet confirmed, need that question answered before any savings figure means anything.

Facilities that commonly satisfy all four include hospitals and healthcare campuses, hotels, multifamily housing, food and beverage processing, and manufacturing plants with continuous process heat.

One category worth a caution, because it is often listed elsewhere as an ideal fit:

  • Data Centres - They have very large, very steady electrical loads, which sounds perfect — but typically little use for recovered heat. Without somewhere for that heat to go, the central advantage of cogeneration is lost. Some sites can put it to work through absorption cooling; many cannot. That is a site-specific question, not a category answer.

What Your Result Means

The quiz reports an operational fit, not a financial result. It tells you whether your building has the physical characteristics that make cogeneration work. What you would actually save depends on your utility rates, which the savings estimator handles separately.

  • Strong Operational Fit— steady hours, real year-round heat demand, and meaningful electrical load. Your profile matches the buildings that see the fastest paybacks. Worth pricing properly.
  • Good Operational Fit — several of the right characteristics are present. A savings estimate using your actual rates will show whether the numbers work.
  • Possible Fit — your building does not show every typical trait, but load, rates, and incentives vary enough between sites that it may still be worth pursuing. Usually a short conversation settles it.
  • Not a Typical Fit Today — almost always one of two things: no natural gas, propane or biogas available at the site, or an electrical load below the range our smallest unit serves. Both are facts about the building rather than judgements about it, and both can change. If you add a gas service, expand, or take on a new process load, the answer changes with it.

A building with limited thermal use does *not* land here on that basis alone. It returns Possible Fit with a note that the thermal load needs review, because a building whose heat use hasn't been properly investigated is still worth a conversation.

Why a Good Building Can Still Receive a Lower Result

The quiz will not return a Strong result to a building that is missing something cogeneration cannot work without — no fuel on site, no year-round use for the recovered heat, or an electrical load below the smallest unit we make. Strong answers elsewhere do not offset those.

When that happens the result names the limiting factor rather than leaving you with an unexplained score. We would rather tell you plainly that one condition is missing than encourage a project that will not perform.

Frequently Asked Questions

Is this a cogeneration quote?

No. It is a screening question set. It asks about your building's characteristics and returns a fit category. No pricing, no equipment selection, and no commitment.

Do I need my utility bills?
What if my fuel is propane or biogas?
My building is in Canada. Can I use this?
How long does it take?